At the foot of the Noor Ouarzazate mirrors, Masen now wants to put batteries to the test. On October 14 the Moroccan Agency for Sustainable Energy launched an international request for bids for a complete battery energy storage systems (BESS) testbed at the complex’s research and development platform.

Estimated at 3.25 million dollars in the notice published by the World Bank, the contract is funded by a grant from the ESMAP program the Bank administers. Bids are due in Rabat on November 27.
The testbed is to test industrial-scale batteries, from their capacity to their aging and their behavior on the power grid, giving the Kingdom a reference platform independent of manufacturers.
Its design was entrusted in May to the Paris firm Kurybees, and everything must be finished before the funding closes at the end of October 2027.
It is there, between the mirrors and the desert, that the question haunting every solar transition will be settled, that of keeping the energy once the sun has set.
Photo: Richard Allaway, CC BY 2.0.
Masen, Banque mondiale - Specific Procurement Notice, Request for Bids: Plant Design, Supply and Installation of the Battery Energy Storage Systems (BESS) Testbed, RFB No: 13/2026/MASEN
Masen, Banque mondiale - Contract Award: Battery Energy Storage System Testbed in Morocco, MA-MASEN-490513-CS-QCBS