The works of the first tranche of a photovoltaic solar plant of 3 megawatts were launched on November 19 in the commune of Lamrija, province of Jerada, for an investment of 30 million dirhams, according to the MAP.
The General Directorate of Territorial Collectivities contributes 26 million of it and the Moroccan Agency for Sustainable Energy (Masen) 4 million. Its subsidiary Masen Services is in charge of realizing the installation within a delay of seven months.
The electricity produced, about 6 gigawatt-hours per year, is equivalent to the consumption of more than 4,000 families of the province. It will be ceded for 25 years to the Regional Multiservice Company of the Oriental.
The project provides in the end for a capacity of 10 megawatts, for a forecast investment of 114.5 million dirhams, connection and access included.
Photo: Philippe Roos, CC BY-SA 2.0.
MAP, via Médias24 - Masen et la DGCT engagent 30 MDH dans une centrale solaire à Jerada